N3 Sewers: Project Update 12.7.2017

December 7, 2017
The construction of our sewer system appears to be progressing smoothly. Tanglewood Dr. north of Fair Oaks is essentially complete and Rose St and Bougainvillea are almost finished, as is North Seclusion Dr.  There is some construction to be done on the south side of Webber St that is included in Phase 2. The plans show Homassassa Rd. to be Phase 3 and work there will begin upon completion of Phase 2.

What’s That Pipe in My Yard?

Some residents have asked “what is that green pipe sticking up in my yard?” Well, that is the connection point where the homeowner’s sewer line hooks up to the utility sewer. The finished installation will be cut off at grade level. Here are some photos:

This is what we’re looking at now…

 

This is a typical clean-out at the connection to the county sewer line.

Anybody Know a Good Plumber?

Although our actual hook-ups are months away, this is probably a good time to start talking to plumbers.  I have contacted several and here (in alphabetical order) are those that have indicated an interest in working in our neighborhood:

One advantage in making early contact with a plumber is to get their advice on the placement of the clean out at your property line.  The contractor (Spectrum Underground) has indicated that they will locate the connection pipe wherever you want it, but once it’s installed it can’t be relocated.  Determining the best location now could save you money down the road!  If you know of other plumbers that are interested, have them contact me and I’ll add their names to the list.

Note: When you speak with the plumbers be sure to tell them OUR SEWERS ARE NOT A VACUUM SYSTEM!
 

List of Certified Plumbers from DBPR

 A listing of state certified plumbers is available at www.myfloridalicense.com: click on “VERIFY A LICENSE”, then “Search by City or County”>Category “Construction Industry”, Type “Certified Plumbing Contractor”>County “Sarasota”> Search.

For Our Do-It-Yourself Neighbors

In a future article I’ll have some tips and guidelines for those ambitious souls that may want to do their own work.

Contact Information

  • construction questions – John Saputo (941) 650-0022
  • Pluris Southgate customer service – (888) 758-7471
  • utility connections – (941) 861-6767   [option 1]
  • financing connection fees – (941) 861-6767  [ option 3]
  • PCSSRP documents

 

Advertisements

Traffic Advisory for N3 Neighborhood

October 26, 2017

CORRECTION: Lockwood Ridge Rd. will have daytime closures for three days (Nov 7,8,9), not three weeks as originally reported.  

Neighborhood Traffic Advisory

An upcoming County project on Lockwood Ridge Road will have that road closed for about 3 weeks days (daytime only). The detour will direct traffic to Tanglewood Drive and other streets in the N3 neighborhood.

The County Project Manager for that project will be sending out a mailer to all N3 residents as well as another 300 or so homes that will be affected later this week and it will explain in more detail what the routes will be for North and Southbound traffic on Lockwood Ridge.

Our contractor is aware of this and will be moving their operations to Bougainvillea Street to lessen the impact of traffic and congestion.

N3 Sewer Construction

Please do not enter an active zone of construction

The contractor has asked that we reiterate the need for safety for the residents and all of those traveling in the areas under construction. There have been several instances of pedestrians and bicyclists entering the work zone to see the work being done. Please do not enter an active zone of construction.

 John Saputo, Project Manager 

941-650-0022

 jsaputo@scgov.net

 

 


Contact Information

  • construction questions – John Saputo (941) 650-0022
  • Pluris Southgate customer service – (888) 758-7471
  • utility connections – (941) 861-6767   [option 1]
  • financing connection fees – (941) 861-6767  [ option 3]
  • PCSSRP documents

Read the rest of this entry »

IRMA Storm Debris Collection Info

October 6, 2017

Sarasota County Status Map

Sarasota County has posted a Storm Debris Pick-Up Status Map to their website. (You’ll notice that our neighborhood is in the area designated N4 – not to be confused with our PCSSRP Area N3).

From today’s Herald Tribune

“Only a little more than 7 percent of roads throughout unincorporated areas of Sarasota County have been cleaned up by debris contractors, according to an interactive map the county has established to track efforts.

The map — updated daily and available online at scgov.net — highlights public, private and state roads and the status of individual segments. Residents can zoom in on the map all the way to their own home and click the segment for an estimated pickup date, anywhere from next week through early December.”

 

N3 Sewers: Project Update 8.15.17

September 20, 2017

Latest Info from Sarasota County

The Phillippi Creek Septic System Replacement Program (PCSSRP) was developed in 2000 to protect public health and to improve water quality in Phillippi Creek, by replacing individual septic systems and small private package waste water plants in many Sarasota County neighborhoods with central sewer service. Over 15,000 septic tanks will be replaced over the life of the project. Approximately 200 residents will be connecting to central sewer in Area N3.

Area N3 is being designed as a hybrid gravity sewer system with two smaller lift stations within the project area. Homeowners will connect to the central sewer system using a conventional gravity lateral rather than maintaining individual low pressure units on each property, as originally planned.

Award of the construction contract was April 25, 2017 to Spectrum Underground. The construction Notice to Proceed was given on May 23, 2017. Construction has begun and completion of the project is scheduled for March 2018.

Crews will continue pipe installation work on Tanglewood Drive and North Seclusion Drive. Work from there will proceed to the North. The Directional drill operations at North and South Seclusion are complete. The recent hurricane has impacted the work, so progression of work has slowed. More crews are expected to arrive in two to three weeks.

Please do not enter an active zone of construction

The contractor has asked that we reiterate the need for safety for the residents and all of those traveling in the areas under construction. There have been several instances of pedestrians and bicyclists entering the work zone to see the work being done. Please do not enter an active zone of construction.

 John Saputo, Project Manager, 941-650-0022

 


Contact Information

  • construction questions – John Saputo (941) 650-0022
  • Pluris Southgate customer service – (888) 758-7471
  • utility connections – (941) 861-6767   [option 1]
  • financing connection fees – (941) 861-6767  [ option 3]
  • PCSSRP documents

Read the rest of this entry »

N3 Sewers: Project Update 7.21.17

July 21, 2017

Latest Info from Sarasota County

The Contractor [Spectrum Underground] has been awaiting permit approval to use the right of way at the intersection of Webber Street and Lockwood Ridge Road as a small materials and equipment staging area. Once the permit is received, the contractor intends to start mobilization to the site.

They are currently forecasting a full start the first week of August. This will include directional drilling at the Seclusion Drive locations. This work will not impact traffic flow, however, when the manhole and gravity pipe installation begins, there will be flagmen directing traffic around the work and slight delays can be experienced.

More information will be posted as it becomes available.

Contact Information

Kate O’Hara, Utilities Connections Coordinator, has provided the following:

  • construction questions – John Saputo (941) 650-0022
  • utility connections: (941)861-6767  – option 1
  • financing connection fees: (941) 861-6767 – option 3

Pluris Water Personal Web Portal

July 6, 2017

The Feb 8th post reported on a conversation with Pluris management personnel.  One of the items discussed during that meeting was the new personal web portal.  Pluris Southgate customers recently received this letter:

Your Personal Portal

The portal uses the AquaHawk platform, which is used by many utilities to help customers manage their water usage.  It is easy to set up and easy to use.  Several months of AMI meter reading detail is necessary to provide enough information on water usage  for all the available options to be used; the stored history of our individual meters  is now available.  Additional help on how to set up your web portal is available at AquaHawk Online Help. Customers can also call the Pluris customer care center at (888) 758-7471 or contact Regional Manager Joe Kuhns at jkuhns@plurisusa.com.

 

N3 Sewers: Project Update 6.23.17

June 24, 2017

Next Steps

Signs of survey markings are showing up throughout the neighborhood as the contractor gets submittals approved and permits pulled.  The first evidence of construction we see will be the directional boring for underground crossings at Bermuda Brook and the two Seclusion Drives.  This is shown on the N3 Phasing Plan June 2017 as Phase 1.  The rest of the project is planned to proceed in numerical sequence.

 

Got questions?

John Saputo, Construction Project Manager for Sarasota County is available to address any questions or concerns you may have.  He can be reached at (941) 650-0022 or email jsaputo@scgov.net

 

 

 

N3 Sewers: Project Update 6.16.17

June 17, 2017

Information from John Saputo, Const. Proj. Mgr.

 

Phillippi Creek Septic System Replacement Program Area N3

The Phillippi Creek Septic System Replacement Program (PCSSRP) was developed in 2000 to protect public health and to improve water quality in Phillippi Creek by replacing individual septic systems and small private package waste water plants in many Sarasota County neighborhoods with central sewer service. Over 15,000 septic tanks will be replaced over the life of the project.

Approximately 200 residents will be connecting to central sewer in Area N3.  Area N3 is being designed as a hybrid gravity sewer system with two standard lift stations and two smaller lift stations within the project area. Homeowners will connect to the central sewer system using a conventional gravity lateral rather than maintaining individual low pressure units on each property as originally planned.

Award of the construction contract was April 25, 2017 to Spectrum Underground. The construction Notice to Proceed was given on May 23, 2017. Construction is slated to begin in late June. Completion of the project is scheduled for March of 2018.

Expect to see evidence of Survey Crews in the area over the next two weeks establishing Right of Way lines and property boundaries. The first signs of construction will be the directional drilling of forcemains for the North and South Seclusion Roads; that work should also be scheduled within the next couple of weeks.

(ed. note: Mr. Saputo has indicated that we can expect these update/advisories throughout the construction process.  Door hangers and roadway signage will also be provided as necessary.)

Saturday’s Cleanup at Red Bug Preserve

May 30, 2017

On Saturday May 27th John Ryan organized a clean up of  the park at Red Bug Slough.  Here’s his summary:

 

Beautiful Day at Red Bug Slough Preserve!

 

The Friends of Red Bug Slough Preserve gathered again last Saturday morning.  It was a perfect spring day – not too warm yet.  It was good to see the water levels back up after the prolonged drought we had just a few weeks ago.

 

Jack and Ronda

 

We shared some blueberry muffins before we took off and made our neighborhood nature preserve just a little bit better.  Scott made a special effort to root out air potatoes.  Ronda searched for fishing line in the lake.  And Chris dug up some concrete rubble that was dumped here decades ago.  Michele found a garden hose – makes you wonder doesn’t it?

old garden hose                                                                                                                                                         fishing tackle

 

 

 

 

 

 

It was a fun and easy day with friends.  Thanks to everyone who joined in… see you there next time.

 

John

 

 

Phillippi Creek Event Tomorrow May 20th at SGCA

May 19, 2017