September 2016 Project Update

September 28, 2016

PCSSRP Status Report (link)

The above link will take you to the County’s August 31, 2016 Status Report.

Highlights:

  • plans and specifications are 100% complete.
  • bid documents will be submitted in September and advertised in October.
  • construction is expected to begin January 2017 and be completed by end of year.

Jaimol Charles, Project Manager, explained that there was some regulatory issues that took longer than expected to get approval.  The issues are now resolved, but the schedule may be extended by a month or so.

I know there are some neighbors having septic tank and/or drain field problems and hopefully this information will help in making decisions whether to replace or repair.  If you’ll refer to the January 13th post (“Drainfield Problems”) you’ll find ideas and resource links that may be helpful.