At today’s Budget Workshop the Sarasota County Commission unanimously approved a staff recommendation to advance the Septic System Replacement plan in Area N3. This vote was necessary because the county’s capital improvement plan is being reshuffled in order to cope with a shortall in surtax revenue, and some projects are being delayed. Today, our project survived.

I am pleased to report that Commissioner Alan Maio reached out to contact me soon after the commission voted and asked me let everyone know he had received our emails. He said he was glad that we did not overwhelm him with email, and more importantly, that none of us were insulting or rude or threatened to kick him out of office if he did not support our project. So to those of you who took the time to contact Commissioner Maio or any of the other commissioners, thank you for representing our neighborhood well.

I would also like to mention that Commissioner Hines responded promptly to the initial email I sent on behalf of the committee Monday evening, and it was he who introduced the motion today that kept our program in the capital improvement plan.

We owe thanks to all of the commissioners, and specifically to Mr. Hines and Mr. Maio, for voting to keep our sewer project going.

Thanks to those neighbors who took the time to email the commissioners, and thanks for being respectful.

Only one step remains: The county commission will be presented a construction contract for its approval, as soon as April. Then, at long last, we should see digging in the streets. I am sure there will be a lot of information in the coming months.

Best regards,
Peter Gentile
Chairman
N-3 Neighborhood Committee

 

 

worth noting

Charles Hines is the only sitting commissioner that was involved in the months of discussion concerning our project.  He met with us several times during the process and  has been very supportive of our efforts throughout.  Comm. Alan Maio is one of the “new guys”, but seems genuinely interested in connecting with us in the neighborhood.  He is the Commissioner for District 4 (our district).

 

Advertisements

Are we on the chopping block?

March 27, 2017

Current status

The December 20 post discussed the last official update of our sewer project: “The design is 100 percent complete with all required permits.  The project is currently advertised for construction bids.  Construction is expected to begin in Spring 2017 with an approximate 9-month construction duration.”  (Additional information can be found in the PCSSRP Monthly Status Report.)

Budget shortfall

Your N3 Committee has been closely following the progress of our neighborhood sewer project.  At the Feb 17 Budget Workshop county staff presented a Capital Improvement Project Prioritization to the Commissioners and the bottom line is there is not enough money for all projects.  So, which ones to cut?  When the PCSSRP was was discussed, Commissioner Maio asked for a report on “literature that has been provided and the expectations of owners.”

Budget Strategy Workshop March 29

This coming Wednesday Mar 29 the County Commission is holding another Budget Workshop.  The meeting starts at 9:00 AM and is open to the public.  Here is  page 85 from the presentation commissioners will see:

What should concerned residents do?

  • You can email commissioners at commissioners@scgov.net and ask them to approve Option 3.
  • Commissioner Maio asked what our expectations are: Let him know we expect to begin this Spring and be completed by December 2017
  • Attend the meeting on Wednesday and speak during either of the two the Open to the Public segments (click here for meeting agenda).
  • If you can’t attend the meeting you can view it by going to  scgov.net “Televised Meetings.”

Presentation for March 29 Budget Workshop

Here’s the full Presentation Package (Phillippi Creek Overview starts on pg. 71).

3-29 Presentation

 

Help! My septic tank is failing!

March 22, 2017

I have recently heard this from several N3 neighbors.  The next thing I’m asked is “when are we going to get our sewers?”  The answer is SOON (I hope!)  But what to do in the meantime?  Well, you gotta do what you gotta do.  The good news is that you may be able to get some help with your repair bills.

Will the County pay for my septic repairs?

Maybe… here’s a reimbursement schedule from the county website:

You can find the complete document here: Property Owner’s Guide  (scroll down to Credit for Septic system Repair)

Sewer installation… when is SOON?

I have not gotten any updates since the December 20, 2016 post.  Here’s an excerpt from that article:

Go to the PCSSRP Monthly Status Report and scroll down to Area N3. Under “Next Major Milestones” we’re told that construction will likely begin in March 2017.  We know that the construction contract bids are currently being reviewed, so this is probably an accurate forecast.

We’re fast approaching the end of March, so the construction start forecast is probably no longer accurate.  As soon as I get an update I’ll post it here.