Here’s the Plan
The official designation for the Area N3 sewer system is CIP #55909. The construction contract was awarded to Spectrum Underground on April 25, 2017 and the Notice to Proceed was given on May 23, 2017. The project was divided into four phases (N3 Phasing Plan June 2017) with the first phase being directional bored conduits at the two Seclusion Dr bridges.
When can we expect service?
The bid specifications for our system allowed 300 days for construction. On May 12, 2017 residents were mailed a “NOTICE OF INTENT TO PROVIDE CENTRAL SEWER SERVICE” letter, with service expected to be available in May 2018.
December 2017
I don’t remember when the first dirt was turned, but residents were happy to see construction activity in the neighborhood. Phase 2 (actually the first phase of digging) seemed to go well, and a Dec 2017 post noted that “Tanglewood Dr. north of Fair Oaks is essentially complete and Rose St and Bougainvillea are almost finished , as is N. Seclusion Dr.”
July 2018
We are now well past the original “service expected” date and we get this message: “The estimated completion of Phase 3 is September of this year” with construction of Phase 4 to begin in October. This update mailer also tells us that Spectrum Underground “is behind schedule with an estimated completion of the entire project in February 2019. So, we are now 9 months behind schedule.
December 2018
The PCSSRP Status Report for fourth quarter 2018 tells us “The contractor [Spectrum Underground] failed to meet the Substantial Completion date of February 17, 2018″. No reason is given for the delay, but “work has begun on Phase 4 (the final phase) and is scheduled to be completed in March 2019”.
April 2019
A Project Update postcard tells us “Construction of the PCSSRP Area N-3 Sewer Project will be finishing soon”. It goes on to say that there’s six weeks of work on Tuttle Ave and then paving and sod restoration will begin in Phase 4. We are now a full year behind schedule… and the estimated completion date is “soon”. A March 2019 Project Status on the County website posted the estimated completion date as May 2019.
Where’s Spectrum?
I can’t remember the exact time frame, but somewhere along the way Spectrum stopped showing up. There was still material at the staging areas, but the workmen and equipment were nowhere to be seen. County workers would occasionally be on site, and Windemuller Electric was working on the lift station electrical panels. I asked one of the County workers what had happened to Spectrum. He said “maybe they’re on another job somewhere”, but he didn’t know for sure.
December 2019
The Dec 2019 Project Update on the County website tells us that construction was complete in October 2019 and that “final project closeout is anticipated for late December 2019”. Indeed, Michael Mylett’s email said the system became available for use on December 31, 2019.
February 2020
So, here we are 1 year 8 months past the original “service available” date on a project that had a 9 month duration. I have never heard an official reason for this overrun, but it certainly seems due to subpar performance by the contractor, Spectrum Underground. There were no catastrophic acts of nature, unknown construction obstacles, or other force majeure factors. The leaking manholes in Phase 4 were most certainly not due to an act of God.
What happened to the inspector?
In April 2017 Jones Edmunds & Associates, Inc. was awarded the contract for Construction Inspection. The duration of the inspection contract was presumably the same as the construction contract, 300 days. The not-to-exceed amount was $319,850, but 17 months later (Sept 11, 2018) the BCC increased that amount to $515, 850.
The Jones Edmunds inspector was not on the job for the last few months of construction. Apparently the county was unwilling to give them yet another increase. So, we spent over a half million dollars, but didn’t have the oversight when we needed it. If the inspector had been on site he might well have spotted the problem with the leaking manholes.
Bottom Line
If the project had been completed anywhere near the original May 2018 date we would not be in this situation. Most, if not all, of N3 residents would have been connected. And we would have paid a fee of $2,627.16, not $3,190.00.
Monday’s post
Next week I’ll recap what we know about Resolution 2019-205, the action that authorized the $563 fee increase.
NOTE: All information in this article is from my personal knowledge or was sourced from Sarasota County documents. If I have misstated or misrepresented anything, let me know and I’ll correct it immediately.